Our Experience
Healthcare:
Government:
Commercial:
Environmental:
|
 |

St. Joseph's HVAC Upgrades
Wheaton Franciscan Healthcare - St. Joseph's Regional Medical Center
5000 W. Chambers St.
Milwaukee, WI 53210
Responsibility: General Contractor
Architect: Eppstein Uhen
Description:The West Addition HVAC upgrades consisted of replacing numerous steam pipe valves throughout the 4,5,6,7, and 8th floors of the West Addition at St. Joseph Regional Medical Center. This work had to be completed 5 rooms at a time for a total of 180 rooms.
St, Joseph needed all the existing valves removed as some were up to 50 years old and had begun to break during normal functions and shutdowns. In order to complete this our construction team had to removal all of the ceilings at the valves, the valves were then abated, replaced, insulated and ceilings re-installed.
|
 |